For most renovations, it will take your designer one to three weeks to provide a design and quote from an initial meeting.
Every person makes decisions at their own pace and ideas often change. Refining the design can take anywhere from a couple of days to several months.
The time it takes to confirm the items on the specifications list is different for everyone. Sometimes it can take a week, whereas sometimes it can take months.
In most cases, we can start work on site six to eight weeks from when the specifications list and project manager meeting are completed.
On average a kitchen renovation would take two to six weeks on site depending on benchtop, splashback and cabinetry choices and whether walls, plumbing and electrical services are moving.
Likewise, depending on material choices and services moving, an average laundry would take one to four weeks to be completed on-site.
A bathroom renovation would commonly take four to six weeks on-site depending on whether the plumbing and electrical services are moving.